FishPass in Traverse City: What's Done and What's Next in 2027

October 15, 2026

FishPass is the $30 million project replacing the Union Street Dam on the Boardman/Ottaway River. In late September 2026 the team said the in-stream work, which took close to two years, was wrapping up. The fencing between Cass and Union streets is staying up through the winter anyway. What's left is the part of the site built for people. That includes the pedestrian bridge, landscaping, river access and a research building. It's all on a timeline that brings this stretch of river back to downtown in 2027, around when the new farmers market pavilion at Lot B opens one block away.

What got finished in the river

Engineering-wise, the hardest part of FishPass was the fish-sorting channel. It's 400 feet long and 30 feet wide. The Great Lakes Fishery Commission's July 2026 update said the foundation slab and headworks were done, with the channel walls due within a month. By mid-August, The Ticker reported that the city called the channel substantially complete. That covered:

  • The headworks
  • The channel walls
  • All 13 water control gates
  • Backfill along the channel

The same article covered the next step. Divers went into the Boardman upstream of the channel to cut off and remove the temporary sheet-pile cofferdam, which had held back water so crews could work in dry sections of the river. A vibratory hammer was scheduled to pull out the rest of the sheet pile through the end of September. High-noise work was limited to 8 a.m. to 5 p.m. on weekdays, and more than 20 vibration and settlement monitors were watching nearby infrastructure. No public report has confirmed the date the last piece came out. The September 22 update from UpNorthLive described all the wet work as wrapping up.

All of this happened after a near-disaster in the spring. In April the Boardman/Ottaway crested around 2,300 cubic feet per second. The fishery commission called it nearly a 500-year flood. Leah McCallum, a spokesperson for the commission, told The Ticker the project was "completely caught up to where we would have been if the flood didn't happen." She gave the credit to local contractors Spence Brothers and Team Elmer's, who worked overtime.

Why the fence stays up all winter

With the river work done, the jobs left on site happen on land. You'll be able to see them from the sidewalk, but you can't use any of them yet.

The first went in on Tuesday, September 29. Crews set the new pedestrian bridge into place along the Boardman. UpNorthLive reported that once the project is complete, people on the bridge will be able to look down at the fish and see how the sorting works. Until then it's a finished bridge behind a construction fence.

Most of the remaining work is planting. The Ticker article cites the city's Bay Brief: the plan calls for 73 native trees, 371 native shrubs and nearly 2,100 live stakes along the shoreline to stabilize the banks. A separate $20,000 contribution pays for 80 more trees at other public locations around the city. The project's earlier phases took out most of the roughly 61 larger trees slated for removal. A few more are coming out this fall near Central United Methodist Church to make room for ADA accessibility improvements.

The research facility on the north bank is the biggest unknown. The two most recent reports give different timing. The Ticker's August article described building it over the winter. UpNorthLive's September report put the office building in phase three, starting next spring. The commission's own schedule runs phase three, covering riverbank construction, site grading and the research building, from late 2026 into mid-2027. It also says the schedule may change.

That building matters because the research is the reason the site exists. Here's how McCallum described the work to UpNorthLive:

"We will be measuring fish populations. How many fish upstream is the right number of fish upstream?"

Where you can walk right now

The city's posted construction instructions for FishPass list these closures:

  • Lot J
  • The south shoreline and riverwalk between Cass and Union streets
  • The southwest Cass Street Bridge stairs, closed at the first landing
  • The docks at that spot

The same notice says the north-side riverwalk and the stairs near the Union Street Bridge stay open, and that pedestrian detour signs will be posted. The notice carries a 2024 date, and the city hasn't posted a newer access map. The signs on site are the best guide to what's open on a given day. The commission also runs a time-lapse camera on the site, so you can see the channel and bridge from closer up than the fence allows.

This fall's salmon stop at Hall Street

If you walked the river in September and wondered where the salmon were, they didn't make it as far as the FishPass site. Under the fisheries management plan for Grand Traverse Bay and the Boardman, returning salmon are harvested in September and October. That happens at the DNR's Boardman River Weir at 118 Hall Street, between the old dam site and the river mouth. The reason, in the DNR's words, is that large numbers of salmon "would lead to major problems in the short section of river between the bay and the dam." Lake trout, brown trout, steelhead and Atlantic salmon are passed upstream of the weir toward Kids Creek and FishPass.

FishPass is also stricter than the structure it replaced. The 1987 fish ladder at Union Street let jumping fish like salmon and steelhead through and stopped non-jumpers like smallmouth bass and walleye. The DNR describes FishPass as a complete barrier to all fish, designed to sort and pass the species managers want while blocking invasive sea lamprey. Testing comes before any of that sorting. The Ticker reports that a commissioning phase, with the channel tested before full launch, follows construction. Decisions about which species pass belong to the Michigan DNR, in consultation with the tribes.

The weir's own numbers show how much the run swings from year to year. The DNR's posted totals end with the 2025 season:

Season Chinook Coho Total salmon harvested
2024 1,426 5,122 6,548
2025 2,647 2,266 4,913

The Chinook harvest nearly doubled from 2024 to 2025 while coho fell by more than half. The DNR hasn't posted 2026 counts yet.

One block of river, three projects

FishPass is one of three projects reshaping the same few hundred feet of downtown riverfront. The city's October Bay Brief shows the Sara Hardy farmers market pavilion under active construction at Lot B, with that lot closed and completion expected in spring 2027. Until then the market runs at Rotary Square, 203 S. Union St.

The third project would tie the first two together. The April flood damaged the riverbank along the alley just north of FishPass. That alley is now being considered for improvements that would connect FishPass with Rotary Square, including a public river overlook. The Downtown Development Authority's August 21 board packet recommended approving extra Rotary Square design and engineering work with Progressive Companies, capped at $29,300. No outcome of that vote has been published, so the overlook is still a proposal.

Here's the near-term calendar for that stretch, based on current reporting:

What Status as of October 2026 Expected
Monroe Street, Randolph to West Front Closed for Phase 3 reconstruction Reopening around Oct. 30, weather permitting
FishPass pedestrian bridge Installed Sept. 29 Open to the public when the project is complete
FishPass site and landscaping Dry, upland work Late spring to late summer 2027, depending on the report
Recreational river access at FishPass Closed Sometime in summer 2027
Lot B market pavilion Under construction Spring 2027
Alley overlook to Rotary Square Engineering proposed Not scheduled

The completion dates differ by source. The commission's spokesperson told The Ticker in August the goal was late spring or early summer 2027. UpNorthLive's September report said the commission had set completion for late next summer. The Ticker's report also said recreational access to the Boardman is expected to reopen sometime next summer.

Nan Ray follows FishPass, the Lot B pavilion and the Rotary Square overlook proposal as their schedules change. If you're thinking about a home or condo near the Boardman and want to know how these 2027 dates affect a particular block, schedule your free consultation.