On Monday, Oct. 26, crews from Team Elmer's were getting ready to start work on Lake Street in Empire. Several residents came out to protest and to talk with the workers, according to The Leelanau Ticker. The plan called for removing a row of mature trees, mostly maples, along the street that same week. By the end of that day the plan had changed, and the trees were still up.
The local coverage gives the credit to the people who signed and showed up, and they earned it. A buried power line and a fixed paving deadline also pushed the village toward the same decision that week. The bigger point for anyone who drives or walks Lake Street is where the water comes from. Lake Street is the low end of a drainage problem that starts up the hill on Wilco Road, and the fix for that stretch is a separate federal project. It isn't scheduled to start before 2027.
What Lake Street's project is for
Lake Street runs north from Wilco Road, the road that comes down from the Empire Bluff trailhead, to the Empire Post Office along the west side of downtown, as the Glen Arbor Sun describes it. That layout explains the whole project. Water that falls on the bluff side follows Wilco Road downhill and then keeps going down Lake Street.
The Leelanau Enterprise reported that the work is meant to address chronic flooding that has sent enough water down Lake Street in past storms to cover the road completely. The Lake Street job is paired with a broader stormwater effort tied to a Leelanau County Road Commission drainage project on Wilco Road.
The Empire Village Council awarded the job to Elmer's Crane and Dozer at its regular meeting in late September. The $248,556 bid came in about $100,000 over the project's original budget estimate. It was still the lower of the two bids the council received, and the vote was unanimous, according to the Enterprise. According to that same Enterprise reporting, which the Sun cited, part of the cost is covered by a Federal Lands Access Program grant secured through a partnership of the Road Commission, the Village of Empire and the National Park Service.
The concerns started at that September meeting. Empire resident Karen Baja raised the number of trees that would come down, and council member March Dye agreed with her before the vote went through.
How the week went
The plan changed fast. Here is the sequence from the three local papers:
- Late in the week of Oct. 19. Ella Skrocki, whose family owns Sleeping Bear Surf, started a petition asking the council to pause the tree removal.
- Over the weekend. Residents went door to door. By Sunday night, Oct. 25, the petition had 264 signatures, the Sun reported. Several residents also contacted Village President Dan Davis directly, according to the Enterprise.
- Monday, Oct. 26. Protesters talked with Team Elmer's crews on site. The village, Team Elmer's and the engineering firm Gosling Czubak then worked out a new plan that met the same drainage goals without cutting the trees, per the Ticker. By the time the Ticker wrote its story, the petition had nearly 300 signatures.
- Later that week. Davis told the village council, "We did not take the trees down."
Three pressures in the same week
The petition asked for more than saving the trees. It asked the village to pause the sidewalk reconstruction too, and it made an engineering argument that fits the street's layout:
"Based on firsthand observations of runoff along this corridor, the primary stormwater problem area extends from the top of Wilco Road to Aylsworth Street. Yet the majority of the proposed runoff mitigation efforts are below Aylsworth, in a comparatively flat area."
The full text, published by the Glen Arbor Sun, also called mature trees "functional green infrastructure" because they intercept rainfall and help water soak into the ground. It asked the village to finish its Wilco Road stormwater planning with Sleeping Bear Dunes National Lakeshore before deciding how much work was needed farther downhill.
The Enterprise's account adds a second pressure. Davis said the engineer called him that Monday after running into a buried electrical line. Consumers Energy couldn't move the line right away and told Davis it would take several weeks. Asphalt isn't available after Nov. 15, so the village could either change the plan or hold up the road. Davis said he made the changes himself because there was no time to wait. "I talked to Martin, the head engineer for us at Gosling Czubak, and we decided we could leave the trees standing," he told the council, as reported by the Leelanau Enterprise.
The petition and the people on the street made the case for keeping the trees. The buried line and the paving cutoff meant the original design couldn't go ahead on schedule anyway. All of it landed within about 72 hours. The Nov. 15 cutoff falls on Sunday.
Skrocki gave much of the credit to the contractor. "I think Elmer's really deserves so much praise in this project because they were able to take their wisdom from projects that they've done historically and their knowledge of runoff and street design and were really able to help the engineer explore a different path forward that could be less intensive and destructive," she told The Ticker. Davis was also glad with the result: "We're very happy with this resolution and that we're able to please the public."
The maples still face a risk
The trees are standing for now, but they aren't safe yet. Davis told the Ticker the trees were first recommended for removal because the construction will probably damage their roots and kill them anyway, and that could still happen. "If those trees do die, they're in the village right away and it will cost us more money to take them out in the future than it would have it we had taken them out now (but) we decided we'd give them a chance," he said.
Skrocki is more hopeful. She sent photos and a description of the project to an arborist friend. He told her the trees could recover, and that aerating the soil could help restore the feeder roots near the surface. She also told the Ticker it could be "years and years" before anyone knows whether the roots were damaged. If the maples leaf out in spring 2027, that's an early good sign. Their condition over the next several summers will be the real answer.
The other half of the plan is on Wilco Road
The petition's main argument was that the water starts uphill, and the federal government has a project there too. Wilco Road appears in the Federal Highway Administration's Michigan program of projects for federal fiscal years 2027 through 2029. It's listed as a roadway resurfacing project with Leelanau County as the applicant, in fiscal year 2027. The M-22 Scenic Byway committee's draft minutes describe the same work as drainage improvements and repaving on Wilco Road from M-22 down into Empire, including the seasonal section from the top of Empire Bluff, with a 2028 timeline.
Here are the two projects side by side:
| Lake Street | Wilco Road | |
|---|---|---|
| Where | Wilco Road north to the Empire Post Office | M-22 down into Empire, including the seasonal stretch from the top of Empire Bluff |
| Who is building it | Elmer's Crane and Dozer for the Village of Empire, designed by Gosling Czubak | Federal Lands Access Program project, applicant Leelanau County |
| Scope | Drainage and road work on a street that has flooded over in past storms | Drainage improvements and repaving |
| Timing | Crews were preparing to start the week of Oct. 26; asphalt is unavailable after Nov. 15 | Federal fiscal year 2027 in the FHWA program; 2028 in the byway committee's notes |
For people in Empire, this means the Lake Street work comes first, and the uphill stretch the petition pointed to gets its own work a year or two later. The redesigned Lake Street plan, the trees left in place and the Wilco Road work will all be tested together in the first heavy storms after both projects are finished. If you hike Empire Bluff, the seasonal road to the trailhead is part of that federal project.
Empire's drainage plan is also part of the bigger picture for anyone weighing a home in the village. Which streets were rebuilt, when the next phase arrives and how a corridor looks once the work is done all matter. If you'd like to talk through what the Lake Street and Wilco Road projects could mean for a property you own or are considering in Empire, Nan Ray is glad to walk through it with you. Schedule your free consultation.